17 Years
From concept to operation
₹13,366 Cr
Total project investment
Oct 2025
Bihar's first metro operational

The Vision Behind Patna Metro

Patna, the capital of Bihar and one of India's oldest living cities, has long faced severe traffic congestion due to rapid urbanisation. With an urban agglomeration population exceeding 2 million, the city's road infrastructure was struggling to keep pace with demand.

The idea of a metro rail system for Patna was first explored in 2009, when the Delhi Metro Rail Corporation (DMRC) conducted a comprehensive feasibility study. The study confirmed the technical and financial viability of a rapid transit system.

After years of planning, approvals, and stakeholder consultations, the project received final clearance from the Union Cabinet in February 2019. Prime Minister Narendra Modi laid the foundation stone on February 17, 2019, marking the official launch.

PMRCL was established as a Special Purpose Vehicle jointly owned by the Government of India and the Government of Bihar, with DMRC serving as the General Consultant.

Project Milestones

  1. Milestone

    Feasibility Study

    Delhi Metro Rail Corporation (DMRC) conducts the first feasibility study for a metro rail system in Patna to address growing urban mobility needs.

  2. Milestone

    Project Proposed

    The Bihar government formally proposes the Patna Metro Rail project as part of its urban development agenda.

  3. Approval

    State Cabinet Approval

    Bihar state cabinet approves the Patna Metro Rail project. DMRC is engaged as General Consultant and DPR work begins.

  4. Construction

    Central Clearance & Foundation Stone

    Union Cabinet clears the ₹13,365.77 crore project. Prime Minister Narendra Modi lays the foundation stone on February 17, 2019.

  5. Milestone

    PMRCL Incorporated

    Patna Metro Rail Corporation Limited (PMRCL) is formally incorporated as the special purpose vehicle to execute and operate the project.

  6. Construction

    Civil Construction Begins

    Ground-breaking civil construction begins across elevated sections. Viaduct and pier construction commences on Corridor 2 priority stretch.

  7. Construction

    Elevated Structures Progress

    Significant progress on elevated viaducts on both corridors. Rolling stock procurement processes initiated. TBM procurement underway.

  8. Construction

    TBM Tunneling Begins

    Tunnel Boring Machines launched for underground sections through central Patna. Work accelerates on priority elevated stretch of Blue Line.

  9. Milestone

    First TBM Breakthrough

    A major milestone — the first TBM successfully breaks through between Moin-ul-Haq Stadium and Patna University stations.

  10. Operational

    Operations Begin 🎉

    Patna Metro becomes partially operational on October 6, 2025. Bihar's first metro runs! The priority stretch of the Blue Line begins revenue service.

  11. Operational

    Blue Line Extended

    Blue Line extended to Malahi Pakri Metro Station on July 2, 2026, enhancing connectivity for more commuters.

  12. Target

    Full Network (Target)

    Complete Phase 1 network including all Red Line stations and remaining underground sections targeted for full completion.

Current Status — July 2026

✓ Operational

Blue Line priority elevated stretch in revenue service. The section extends from New ISBT to Malahi Pakri, with the most recent extension opening July 2, 2026.

🚧 Under Construction

Red Line and remaining Blue Line underground sections actively under construction. Full Phase 1 completion targeted by 2027–2030.